The new construction of the footpath and cycle path was divided into three construction phases. Cars and cyclists or pedestrians were spatially separated from each other. Over a total length of approx. 5 km, 45 field access roads were constructed in asphalt and 900 m of concrete channel were laid. In May 2023, to coincide with the start of summer, the cycle path was opened to traffic.
Efficient teamwork
In this project, too, work was done hand in hand and economically. The construction project required 5,000 m³ of fill soil, which was obtained from another construction site of the Osnabrück branch. In addition, the in-house construction materials laboratory accompanied the project with regard to quality assurance in earthworks.