Skip to content

Rothof viaduct, Rottendorf

Facts and Figures
Company PORR GmbH & Co. KGaA
Principal Northern Bavaria branch of the Autobahn GmbH des Bundes
Location Rottendorf - Germany
Type Bridge construction
Runtime 04.2017 - 10.2021

Construction of replacement Rothof viaduct on the A7

The PORR Civil Engineering division has built a solid construction replacement for the Rothof Viaduct in Lower Franconia, between the Würzburg-Estenfeld junction and the Biebelried intersection. The original structure was erected in 1965 as a single-piece composite steel cross-section; the cross-section of the new prestressed concrete structure is divided into two parts. The work included pile foundations, the construction of superstructures using the place and thrust method and the lateral launch of the 17,760 tonne second superstructure over 19.75m. The project is a prime example of sophisticated, high-precision bridge construction.

The A7 is the longest motorway in Germany and one of the most important north-south axes in Europe. The road surface and bridges need replacing in many places and the number of lanes have to be increased to six to accommodate the steadily growing volume of traffic. The damaged Rothof viaduct, which spans the railway lines between Rottendorf and Würzburg, Fürth and Würzburg, and the communication road between Rothof and Rottendorf, was also dismantled by PORR between 2017 and 2021 and replaced by a new viaduct at the same location.

High-precision work and a safe sideways shunt
Separate 410m-long concrete box girders were constructed as a superstructure on both carriageways. In preparation for the 6-lane expansion, the lane width is 14.50m for each carriageway.

Watch our video about the project in Vimeo: 

The superstructures were constructed using an approximately 36m long launching nose by means of the place and thrust method over 15 increments with a maximum individual length of 30m. They sit on two abutments and seven bone-shaped column axes. The largest field spans are 60m and the column heights are between approx. 12.5m and approx. 25.5m. The new structure is founded on large-diameter piles with a diameter of 1.50m and lengths of up to 22m.

Since road traffic on the A7 had to be maintained at all times, in the first construction phase, the Fulda carriageway was constructed in a temporary replacement position next to the existing structure on auxiliary columns. All traffic on the A7 was redirected along this temporary route while the existing structure was completely dismantled. The final substructure abutment columns were subsequently erected for both carriageways and the second superstructure for Würzburg was constructed. Finally, the superstructure for Fulda, which was stored in a temporary replacement position, was launched laterally into its final position.