A100, Berlin

Facts and Figures
Company PORR Verkehrswegebau GmbH
Principal Local Government Department for Urban Development
Location Berlin - Germany
Type Highway
Runtime 10.2009 - 12.2024

Expansion of the Berlin ring road

The Berlin branch was commissioned by Autobahn GmbH des Bundes with Lot 11a in the 16th construction section of the A100 in Berlin. The contract includes the road construction expansion of the previous engineering sections 1-7. In the first section, a 1.7 km long trough structure will be expanded into a six-lane motorway section with hard shoulder; in the second section, the road construction work in the "Grenzallee" tunnel will be realised.

The main artery in Berlin's road network

The A100 federal motorway is one of the main arteries for Berlin's long-distance, regional and urban road network. With the 16th construction phase, it will be extended by another 3.2 km long section. This section runs from the Neukölln motorway junction to the Am Treptower Park junction. In this way, the eastern districts of Berlin will be better connected to the central ring road and the A113, and long-distance connections will also be improved. The development of the engineering structures handed over includes the construction of a complex drainage system, the base courses made of concrete and unbound natural rock, as well as the construction of the carriageway in asphalt construction in open cut (trough construction) and in the tunnel area.

Logistical requirements demand precise coordination

Restricted access to the construction site and a continuous, up to 2 m high paving of the central strip made of in-situ concrete place high demands on the logistical planning of the project. The resulting complex construction sequences and logistical as well as runtime challenges are solved by the construction site team with precision and shoulder to shoulder.

Further construction sections of the A100 for Oevermann

At the beginning of 2022, work started on the first asphalt sections Lot 11a, while the first asphalt application in the "Grenzallee" tunnel was realised in April 2023. But that's not all: since March 2023, the traffic route construction team has also been building the emergency walkways as reinforced concrete caps with air-entrained concrete. The following construction phases concern the connection of the new section to the Neukölln motorway junction and the connection to the Am Treptower Park junction. PORR is building in a familiar environment: the trough structure Lot 5 has already been built by PORR structural engineering and a further section with the lot 6 is currently being produced.