Skip to content
Press / news

A100 Berlin: Progress on the construction of the road trough in lot 6 of the 16th construction phase

On behalf of the federal motorway authority Die Autobahn GmbH des Bundes, PORR Ingenieurbau is building another section of the A100 extension in Berlin in a joint venture with PORR Spezialtiefbau GmbH. Lot 6 of the 16th construction phase will extend the A100 motorway by around 255m. The construction section extends from the Neukölln motorway junction to the "Am Treptower Park" junction. Lot 6 includes the construction of a 225 m long road tunnel as well as the Ringbahn railway overpass.

PORR is building another section of the A100 motorway extension in Berlin.

© PORR

The extension of the A100 is intended to better connect the eastern districts of Berlin to the central ring road and the A113 motorway. An important milestone was already reached in November 2022 with the commissioning of the Ringbahn bridge. The team is currently working on the construction of the 225-metre-long road tunnel, which will later lie at a depth of up to seven metres.

Groundwater poses particular challenges

One of the biggest challenges of the project was that the construction work for the road trough had to be carried out in the area of the groundwater. Trough excavation pits had to be constructed in order to prevent damage to the surrounding area caused by large-scale groundwater subsidence. For this purpose, construction pit walls were made from diaphragm walls. The underwater concrete base is anchored back with threaded anchor piles against the uplift forces. Specialist divers were deployed to ensure the work was carried out safely under water. In September 2023, the trough construction pits were drained after successful pumping tests, which proved that the specified tightness criteria had been met.

Trough structure in progress

The actual trough structure for the future motorway has been under construction since September 2023. The three transverse bulkheads have already been successfully dismantled and the trough base of the three closing blocks has been completed. Intensive work is currently underway to realise the trough.

Media

Here you can find all of the materials related to this press release. Maybe you still have additional questions? Simply contact us. We look forward to providing you with answers.

Contact
Team Unternehmenskommunikation