A66 Salzbachtal Bridge: Second cycle of five completed for north bridge

While the final work on the southern Salzbachtal bridge on the A66 in Wiesbaden is in full swing for the opening to traffic in December, the northern Salzbachtal bridge has now also literally picked up speed: On 17 October 2023, the second cycle was advanced. The new construction of the Salzbachtal Bridge, which is an important piece of the puzzle in the infrastructure network of Wiesbaden and the region, is being carried out by the ARGE PORR/Plauen Stahl Technologie on behalf of the federal motorway company Autobahn GmbH.

On 17 October 2023, the northern bridge reached the first pier.

© PORR

With an average speed of ten metres per hour, the northern Salzbachtal bridge pushed itself about 50 metres across the Salzbachtal valley on 17 October. It took six hours to advance the second cycle. An important milestone for the entire project team, which was achieved routinely and safely thanks to the experience and close and trusting cooperation of the ARGE. As with the south bridge, the north bridge was also pushed in with the help of hydraulic presses and steel cables: The steel section reached the first pier via hydraulic cushions. The next shifting is planned for January 2024.

South bridge shortly before opening to traffic

In December 2023, traffic should once again be rolling over the southern Salzbachtal bridge. Work is in full swing: sealing work on the southern superstructure is currently underway, the construction of the caps has been completed on the superstructure, as has the asphalt work on the eastern and western sections to the southern Salzbachtal Bridge. The team is working in close cooperation towards the opening to traffic.

Media

Here you can find all of the materials related to this press release. Maybe you still have additional questions? Simply contact us. We look forward to providing you with answers.