L159, Schöneseiffen/Hellenthal

Facts and Figures
Company PORR Verkehrswegbau GmbH
Principal Straßen NRW
Location Schöneseiffen/Hellenthal - Germany
Type State road
Runtime 10.2022 - 05.2023

Demanding road rehabilitation between Schöneseiffen and Hellenthal Realised on schedule

On behalf of Straßen NRW, the Düren branch rehabilitated the L159 rural road between Schöneseiffen and Hellenthal. The challenging project in the heart of the Eifel stretched over a distance of about 4.5 km and included both the full expansion and the elevated paving of the road. Always good for a surprise: the weather in the Eifel.

The client, Straßen NRW, was very keen on a quick implementation of the construction work, as the geographical location in the Eifel region only allows diversions over long distances. In this project, the transport route engineering team once again succeeded in combining quality and speed and quickly completed the rehabilitation of the L159 over a total distance of 4.5 km.

Timetable always in view

The construction sections two and three on a length of 2.9 km were completed within only three weeks. This required precise coordination of work running in parallel, with one section being milled and the other asphalted at the same time. Despite some challenges, the professionals managed to complete all preparations in time for the waiting asphalt crew to start smoothly.

In total, impressive amounts of materials were used to restore the rural road. The asphalt base course comprised 8,500 t, the area amounted to 32,000 m2. In addition, 16,000 t of frost protection material was used and 16,500 t of soil was removed.

Weather conditions in the Eifel made work difficult

The weather conditions in the high location in the Eifel presented a special challenge. Snowfall during the night ensured that the road was covered in white within a few minutes. was covered with snow. Two construction sections were even asphalted in driving snow, whereby the second section took place at the end of April. The low point of the temperatures was an icy -14 ° Celsius.

Customer requirements "fastest possible rehabilitation" fulfilled

Despite the adverse weather conditions and the tight schedule, handover took place as planned to the client. The team from Düren proved maximum efficiency, especially during the hard winter working season. Performance and shoulder to shoulder.