At the end of April, the construction team reached the final depth of 24 metres. The concreting of blocks 1.1. to 1.4 of the structure floor was successfully completed in June.
The largest concreting took place on 24 July 2024 with the construction floor 7.4. & 7.5: Around 1,350 m3 of concrete and 400 tonnes of reinforcement were used. 40 PORRians worked in shifts from 5 a.m. to midnight and mastered the tight schedule of this demanding task with flying colours.
Our video provides exciting insights into the first concreting work on blocks 1.1/1.2 and the construction progress.