Skip to content
Press / news

High demands on nature conservation and deadline reliability: special civil engineering work at Straubing harbour DGNB-certified

As part of the Donau expansion between Straubing and Vilshofen, the harbour basin in the port of Straubing-Sand is being deepened. In the invitation to tender issued by the Zweckverband Hafen Straubing-Sand, the Stuttgart-based Stump-Franki subsidiary secured the contract for Lot 1, which comprises the reinforcement of the existing sheet pile wall with 1076 permanent grouted anchors. The German Sustainable Building Council (DGNB) awarded Stump-Franki the pre-certificate "Sustainable Construction Site - Special Civil Engineering" for its very good performance in the areas of construction site organisation, resource protection, health & social issues and quality of construction.

In order to disrupt port operations as little as possible, the anchors are produced exclusively from a 42 x 12 m working pontoon. © Sennebogen Maschinenfabrik GmbH

 

Permanent anchors secure the statics of the sheet pile wall

The Danube expansion between Straubing and Vilshofen is a long-planned decade-long project with two main objectives. Firstly, the flood protection level is to be raised from an approximately 30-year flood to a 100-year flood. Secondly, navigation conditions on the important federal waterway will be improved. Among other things, the draught at low water will be increased by at least 20 cm, between the Straubing lock and the port of Straubing Sand even by 65 cm. Since the existing sheet pile walls are statically subjected to considerably more stress due to the deepening of the harbour bottom, a reinforcement of the sheet pile walls is necessary before dredging. The additional anchor layer consists of 1076 grouted permanent anchors spaced at 1.0 m intervals. The lengths vary between about 18.50 m and 29 m, the anchor steel diameters are 40 mm, 50 mm and 63.5 mm. As the anchor heads are located in the sheet pile valley in each case, waling is not required.

High demands on nature conservation and schedule reliability

Branch manager Stefan Lechelmair emphasises the high organisational and logistical challenges for his team: "In order to disrupt port operations as little as possible, the anchors are produced exclusively from a 42 x 12 m working pontoon. The required material is lifted with the help of a crane from a temporary storage facility on land onto a supply pontoon, which is then moved next to the work pontoon." In order to guarantee deadlines and achieve a high daily output, work has been carried out in two shifts since January. The requirements for environmental protection and nature conservation as well as timely completion are also high. For example, no substances are allowed to get into the Danube water. The drilling material is collected in rubble troughs, brought ashore with the supply pontoon and disposed of properly. As the harbour area is partly located in a bird sanctuary, the noise and sound-intensive work in these areas had to be completed by the beginning of the official breeding season on 1 March.

Media

Here you can find all of the materials related to this press release. Maybe you still have additional questions? Simply contact us. We look forward to providing you with answers.

Contact
Team Unternehmenskommunikation